During which of the following process groups is the preliminary project risk assessment performed?
Answer : B
During which of the following process groups is the availability of required resources for the project determined?
Answer : D
Which of the following describes the point in time when resources can be assigned to scheduled tasks?
Answer : C
In which of the following organization types is it LEAST likely that a conflict regarding competing demands for resources would take place?
Answer : D
Which of the following elements does a project charter contain?
Answer : A
A project can be defined as which of the following?
Answer : D
Which of the following elements would be needed to prepare an effective project scope document?
Answer : C
Which of the following should be created in the project closing documentation? (Select
Two).
Answer : AC
Given the circumstances below, which of the following would be the BEST action for the project manager to take?
1. One of the key stakeholders disagrees with the project.
2. Two of the key staff members refuse to work with each other.
3. The budget for the project has been reduced.
4. The scope of the project has changed.
Answer : C
Two of the stakeholders cannot agree on the project timeline or budget. The project is critical to the success of the company. Which of the following actions should the project manager take NEXT?
Answer : A
Several managers are sharing a project team member, which is impacting the progress of both projects. Which of the following BEST describes the situation?
Answer : D
Which of the following occurs during a project kick-off meeting? (Select Two).
Answer : D,E
A project manager has failed to obtain the necessary permits from the local building commission. The project has been stopped because of a failure to understand the importance of:
Answer : C
A project budget has been reduced by 10 percent, but the project has a critical deadline.
Which of the following should the project manager do FIRST to complete the project on time?
Answer : B
Key resources on a project are being shared. The stakeholders are aware of the shared resources and do not expect this to impact the progress of the project. In which of the following should the shared resource be documented?
Answer : D
Have any questions or issues ? Please dont hesitate to contact us