Test Management -
Which one of the following metrics to be produced needs traceability between the test cases and each item in a proper test basis?
Number of correct responses: 1 -
K2 1 credit -
Answer : A
Test Management -
Which of the following statements best describes an appropriate approach for managing exploratory testing?
Number of correct responses: 1 -
K2 1 credit -
Answer : B
Test Management -
You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:
I. Availability of re-usable test systems and documentation from previous, similar projects
II. Unexpected timing of components arrival
III. Stability of the integration test team (no turnover)
IV. Many and geographically distributed sub-teams
Which of the following statements is true?
Number of correct responses: 1 -
K2 1 credit -
Answer : C
Test Management -
Assume you have some data related to confirmation testing during system testing of a past project.
In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times.
You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 person-hours.
Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?
Number of correct responses: 1 -
K3 2 credits -
Answer : A
Test Management -
The following chart plots the cumulative number of defects opened against the cumulative number of defects closed during system testing of a software product.
Answer : D
Test Management -
You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.
At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.
Which of the following statements is true in this context?
Number of correct responses: 1 -
K4 3 credits -
Answer : B
Test Management -
Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?
Number of correct responses: 1 -
K2 1 credit -
Answer : D
Test Management -
For which of the following activities would the costs be classified as a cost of detection?
Number of correct responses: 1 -
K2 1 credit -
Answer : A
Which of the following statements represents the most effective contribution of the stakeholders to the completion of the failure mode analysis table?
Answer : B
Test Management -
You are performing a quality risk analysis for a CSCI (Computer Software Configuration
Item) used to implement a CBIT (Continuous Built-In Test) module of a safety-critical system.
During the quality risk analysis you are trying to identify the ways in which failures of the
CBIT module can occur, for each of them trying to determine the potential causes and likely effects, and the risk level (calculated as the product of three factors: severity, occurrence and detection).
Which of the following risk analysis techniques are you working with?
Number of correct responses: 1 -
K2 1 credit -
A. A lightweight product risk analysis technique
B. Failure Mode and Effect Analysis
C. Wide Band Delphi -
D. Cost of Exposure -
Answer : B Topic 3, Reviews
Reviews -
Which of the following factors could negatively influence a review?
Number of correct responses: 1 -
K2 1 credit -
Answer : C
The main objectives the senior management team wants to achieve are:
- to reduce the costs associated with dynamic testing
- to use reviews to ensure that the project is on course for success and following the plan
- to use reviews as a well-documented and effective bug-removal activity following a formal process with well-defined roles
- to determine the effectiveness of reviews in terms of phase containment
- to improve phase containment effectiveness
Which of the following answers would you expect to describe the best way to achieve these objectives?
Number of correct responses: 1 -
K4 3 credits -
Answer : D
Reviews -
You are a Test Manager working for a software organization where reviews have never been applied. After a meeting with your managers examining a business case for reviews,
(including their costs, benefits, and potential issues), the management finally decides to adopt formal reviews for future projects.
You have been given a budget that you have spent to provide training in the review process and to introduce the review process on a pilot project.
On that pilot project the introduction of reviews has been very positive in terms of positive involvement from all the participants. All the reviews applied to different documents have been very effective for their purposes (especially at revealing defects).
Which of the following answers describes an important success factor for the introduction of formal reviews which is missing in this scenario?
Number of correct responses: 1 -
K4 3 credits -
Answer : C
During the follow-up phase the following conditions are checked:
X1. The code has been completely reviewed
X2. All the identified defects have been correctly fixed and the modified code has been compiled successfully and run through all the static analyzers used by the project without warnings and errors
X3. The modified code is available under the configuration management system with a new version number for the specified CI
If these conditions are fulfilled then the review process terminates.
Which of the following characteristics of a formal review is missing in this description?
Number of correct responses: 1 -
K2 1 credit -
Answer : D
Reviews -
You are the Test Manager of a project that adopts a V-model with four formal levels of testing: unit, integration, system and acceptance testing.
On this project reviews have been conducted for each development phase prior to testing, which is to say that reviews of requirements, functional specification, high-level design, low- level design and code have been performed prior to testing.
Assume that no requirements defects have been reported after the release of the product.
Which TWO of the following metrics do you need in order to evaluate the requirements reviews in terms of phase containment effectiveness?
Number of correct responses: 2 -
K3 2 credits -
Answer : AE