Certified Implementation Specialist - Strategic Portfolio Management v1.0

Page:    1 / 4   
Exam contains 60 questions

What does the project status report allow project managers to do? (Choose two.)

  • A. View the project Gantt chart
  • B. Show historical trend of project KPI's
  • C. Print as a PDF attachment
  • D. View the WBS


Answer : BC

What is a resource event?

  • A. A non-scheduled activity impacting capacity.
  • B. A block of time that a resource spends on a task.
  • C. An external event.
  • D. An event scheduled by a project manager.


Answer : A

What is the demand workbench used for? (Choose two.)

  • A. Approving ideas
  • B. Approving demands
  • C. Comparing and prioritizing demands against other demands
  • D. Comparing demands with portfolios


Answer : CD

If a user creates a new demand from the demand workbench, what state will the system save the record in?

  • A. approved
  • B. open
  • C. draft
  • D. qualified


Answer : C

What is the formula for Committed Utilization?

  • A. Allocated Hours/Capacity
  • B. Assigned Hours/Capacity
  • C. Confirmed Hours/Capacity
  • D. (Allocated Hours + Confirmed Hours)/Capacity


Answer : D

The RIDAC workflow can be modified by using which recommended feature?

  • A. Project Form
  • B. Flow Designer
  • C. Service Catalog
  • D. Workflow Editor


Answer : D

Which stage of the Now Create methodology includes Transition, Mobilize, Prepare and Conduct?

  • A. Prepare
  • B. Transition
  • C. Initiate
  • D. Close


Answer : B

Which artifacts can be linked to either a program, a portfolio, both, or neither? (Choose two.)

  • A. Demands
  • B. Stories
  • C. Projects
  • D. Test cases
  • E. Operational plans


Answer : AC

Which role is needed to group related projects and demands?

  • A. it_project_user
  • B. it_project_manager
  • C. it_demand_manager
  • D. it_program_manager


Answer : D

Using the Request type field on a resource plan, which options can be used to request a resource? (Choose three.)

  • A. Day
  • B. Person Days
  • C. Hours
  • D. FTE
  • E. Month


Answer : BCD

What role can configure the default columns in the project planning console? (Choose two.)

  • A. admin
  • B. it_pps_admin
  • C. it_project_manager
  • D. it_console_admin


Answer : AB

A checklist item record provides a name and what other element?

  • A. Status field.
  • B. Percent complete field.
  • C. Complete field.
  • D. Short description field.


Answer : C

Which related lists should primarily be used to capture financial data in a project? (Choose two.)

  • A. Programs
  • B. Cost Plans
  • C. Monetary Benefit Plans
  • D. Risks


Answer : BC

Which demand category would a demand manager select, if they need to create an enhancement?

  • A. Defect
  • B. Operational
  • C. Change
  • D. Strategic


Answer : D

In which table can you find cost information for a specific fiscal period?

  • A. cost_plan_breakdown
  • B. expense_line
  • C. pm_project
  • D. cost_plan


Answer : A

Page:    1 / 4   
Exam contains 60 questions

Talk to us!


Have any questions or issues ? Please dont hesitate to contact us

Certlibrary.com is owned by MBS Tech Limited: Room 1905 Nam Wo Hong Building, 148 Wing Lok Street, Sheung Wan, Hong Kong. Company registration number: 2310926
Certlibrary doesn't offer Real Microsoft Exam Questions. Certlibrary Materials do not contain actual questions and answers from Cisco's Certification Exams.
CFA Institute does not endorse, promote or warrant the accuracy or quality of Certlibrary. CFA® and Chartered Financial Analyst® are registered trademarks owned by CFA Institute.
Terms & Conditions | Privacy Policy