You are a project manager who uses Project Professional 2013.
You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project.
The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee of $20.
You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time.
What should you do?
Answer : B
You are a project manager who uses Project Standard 2013.
Your project is approved, and you identify named resources to replace the generic resources for your project tasks.
You need to update the project schedule to assign the named resources to their appropriate tasks.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
Answer :
Explanation:
Box 1:
You use Project Professional 2013 to manage a project schedule which includes all task relationships.
The resource who is assigned to the "Develop software delivery" task is no longer available to work on your project. You can find another resource to perform this task, but you are not sure when the resource will become available.
You need to know which future tasks could be affected as a result of the resource leaving your project.
What should you do?
Answer : D
You are a project manager for a software development company. You use Project
Professional 2013.
You manage an integration project, and you discover that you need to add additional resources to the integration tasks in order to meet your development complete milestone date. The project is behind schedule, so you must shorten the duration of the integration development work.
You identify two additional resources to work on the integration task. When you add these resources, your task now shows it will complete three days ahead of schedule, which leaves a contingency window for issues that may arise.
In order to shorten the duration of the task when the resources are added, you need to set the task type before adding the resources.
What should you do?
Answer : C
You are a Project Manager who uses Project Professional 2013.
You manage a critical project, which is synchronized with a Microsoft SharePoint Task List.
One of your team members has changed a task priority to High in SharePoint, and you do not see the changed data in Project Professional 2013.
What should you do?
Answer : B
Your company uses Project Professional 2013.
You are scheduling two tasks. One task is named Test Solution, and the other task is named Create Solution Test Plan. You want the Test Solution task to start three working days after the finish date of the Create Solution Test Plan task.
You need to set up a dependency between these two tasks.
What should you do?
Answer : D
Your company uses Project Professional 2013. You are a program manager who has a master project created for your program.
Currently you are seeing the critical path for each independent project in the master project. As a program manager, you want to ensure the resources are properly applied to successfully complete the program.
You need to display the critical path for the entire program instead of each independent project.
What should you do?
Answer : A
You are a program manager for a complex software development project. You use Project
Professional 2013 to manage your project. Your resources work on many different projects across the program, and you need to resolve resource over allocations. Your project team uses a resource pool to manage resources.
Resource1 has been assigned to assist on a project that is on the critical path. After assigning Resource2 to the task, you notice that Resource1 is over allocated during the month of November. Project A, which is on critical path, takes priority over Project B, which
Resource1 is also assigned to.
Using resource leveling in Project Professional 2013, you need to resolve the over allocation for Resource1 for the month of November only.
What should you do?
Answer : A
You are using Project Standard 2013.
Management wants to see an overview of your project that shows the overall start and finish dates, total duration, and the name of the project. They want to see this information in a simple layout that does not include task details.
You need to show one line item that displays all the requested information in the Gantt view.
What should you do?
Answer : D
You are a project manager, and your organization uses Project Standard 2013.
You have created a non-working day in a resource's calendar; however, the HR department notifies you that the resource will work that day after all.
You need to reflect this change in the project in the most efficient manner.
What should you do?
Answer : C
You are managing a project using Project Professional 2013.
Your project schedule is showing task overallocation indicators in the Gantt chart view. You navigate to the Team Planner view to investigate more details regarding the over allocations.
You discover that the BA1 resource is overallocated and you need to see all assignments with details for BA1 to understand their current workload before making any assignment changes.
What should you do?
Answer : B
You are a project manager, and you successfully complete a server consolidation project for one of your data centers. You use Project Standard 2013 to plan and track the work.
Your manager wants you to begin similar projects on two other data centers. You need to create a template based on the plan you used to manage the first data center consolidation project.
You need to ensure that the template has all baseline and actual data values removed.
What should you do?
Answer : D
You manage a project by using Project Professional 2013. Your project is updated with changes to the baseline for selected tasks.
You back up your project fife before you start your next tracking cycle. After completing the tracking cycle, you notice that the baseline duration values on some of the summary tasks are not correct.
You need to correct these values before re-entering the tracking data.
You open the backed up version of the project schedule.
What should you do next?
Answer : D
You are a project manager who uses Microsoft Excel 2013.
Your company decides to migrate all of the current projects in Microsoft Excel 2013 to
Project Professional 2013. They allow all employees to spend 8 hours migrating each project plan. Your current and unique project plan has 462 tasks with duration in days, and resources have been assigned and named. You have a status meeting in two days.
You need to provide your project's information by using Project Professional 2013.
What should you do?
Answer : C
You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks.
You create two manually scheduled tasks and link them in a Finish to Start relationship.
The project team member asks you to increase the duration of the predecessor task.
You notice that the successor task start date is now before the finish date of the predecessor task.
You want the successor task to start after the predecessor finishes.
What should you do?
Answer : D
Have any questions or issues ? Please dont hesitate to contact us